The Flint Parking Structure renovation project will provide structural seismic upgrade, concrete structure repair work, stucco and flashing work, light fixture replacement, upgrade of electrical service, installation of new emergency phone system, sealing and waterproofing work, modernization of elevators, reframing of stairways, replacement of signage and updating of striping for ADA compliance.  This project is using the Lease-Lease-Back delivery method with preconstruction to begin in September 2013 and construction to begin in early 2014.

Project Information as of June 2013:

Project Completion:  December 2014

Project Budget:  $6,613,127

Status:  Design